Basiliere Bridge Replacement
Commonwealth of Massachusetts
Basiliere Bridge Replacement
The Massachusetts Department of Transportation (MassDOT) is replacing the Private First Class (PFC) Ralph T. Basiliere Bridge in Haverhill. Find information and see updates on their website or register for email updates from MassDOT.
Project Overview
MassDOT will replace the PFC Ralph T. Basiliere Bridge to improve safety for all users.
Project Information
Location
Main Street, Haverhill 01835
Ward
Between Wards 2 & 3
Project Type
Streets and Bridges
Project Phase
Construction
Anticipated Completion
2032
Project Manager
MassDOT - Highway Division, Theodore Boyle
Contractor
Middlesex Corporation and Transystems Corporation
Background
Built in 1925, the PFC Ralph T. Basiliere Bridge crosses the Merrimack River in the center of Haverhill. It carries Route 125, locally known as Bridge Street. The bridge rests on seven spans. It has two lanes crossing the river and four lanes at the nearest intersections in Bradford and Haverhill. Each side of the bridge also supports a sidewalk. The bridge is a vital connector for the City of Haverhill: 25,000+ vehicles cross each day. This figure includes heavy vehicles such as trucks, school buses, and Merrimack Valley Transit Authority (MEVA) buses.
All the bridge’s parts show the wear of over a century of service. Even parts users cannot see are in poor condition with the foundations subject to scour. The scour results from the river’s current colliding with the bridge’s piers. As a result, the riverbed around the piers is eroding. Frequent inspections and repairs, like those completed in late February and early March of 2025, keep the bridge safe for all users, but have a real impact on the traveling public such as lane closures and detours.
Project Benefits
- Support present and future traffic needs
- Improve cycling and walking conditions
- Improve the Merrimack River's water quality
- Reduce the number of piers in the river.
- Allow continued boating on the Merrimack during and after construction
- Minimize impacts to nearby properties
- Support utilities while the new bridge is being built
- Provide opportunities for accelerated construction methods to reduce construction impacts
- Provide a look which reflects the old bridge while embracing the new
Construction Updates
Construction updates are provided by MassDOT. Sign up to receive regular updates to your email or visit Traffic and construction updates to view project status and construction and traffic management updates.
Traffic Changes
Throughout construction, there will be one lane in each direction, and one sidewalk crossing the river. The limits of work for project include the bridge and the two nearest intersections. These are Main/Water/Merrimack Street and South Main/Middlesex Street. A short section of Main Street between Merrimack Street and Ginty Boulevard is also included.
Updates are provided by MassDOT. Sign up to receive regular updates to your email or visit Traffic and construction updates to view project status and construction and traffic management updates.
Financing
This project is funded through state and federal programs:
- 2026 Transportation Improvement Program (TIP) for the Merrimack Valley Metropolitan Planning Organization
- National Highway Performance Program (NHPP)
Community Engagement
MassDOT welcomes any questions you may have and encourages that you sign up to receive regular updates to your email.
Visit Documents and meeting materials to view all public meetings' flyers, presentations, and minutes.
Learn More about the Basiliere Bridge Replacement
Basiliere Bridge Replacement Work in Haverhill Begins This Week—Mostly Out of Sight (WHAV, October 5, 2025)
MassDOT to Demolish Major Century-Old Bridge in Haverhill (Construction Equipment Guide, August 4, 2025)
State Names Builder of Basiliere Bridge; 6-Year Project Starts In Fall; Here’s How it Affects You (WHAV, August 3, 2025)
MassDOT Board Approves $251 Million Replacement of Basiliere Bridge in Downtown Haverhill (Streets Blog Massachusetts, August 1, 2025)
Mayor’s Office Calls Temporary Closing of Basiliere Bridge Without Notice ‘Unacceptable’ (WHAV, May 20, 2025)
Basiliere Bridge replacement leaves sailors less room (Eagle Tribune, May 14, 2025)
New Traffic Pattern on Haverhill’s Basiliere Bridge After Repairs to Keep it Safe Until Replacement (WHAV, March 6, 2025)
State Completes Installation of Six Beams at Basiliere Bridge; Full Closing Daytime Sunday (WHAV, February 25, 2025)
Basiliere Bridge repairs will deliver detours (Eagle Tribune, February 15, 2025)
Planned Lane Closing This Weekend on Basiliere Bridge Delayed a Week Due to Expected Poor Weather (WHAV, February 12, 2025)
To Keep Basiliere Bridge Safe Until Replacement, Work Feb. 14-16 Detours Southbound Traffic (WHAV, February 8, 2025)
Resident Opinion Drives Design For Haverhill’s Basiliere Bridge Rebuild (WHAV, May 30, 2024)
Basiliere Bridge Replacement Public Outreach Meeting - May 29, 2024 (HC Media, May 29, 2024)
State to Unveil Latest Replacement Basiliere Bridge Design at Haverhill Hearing May 29 (WHAV, May 13, 2024)
Basiliere Bridge replacement project to begin next year (Eagle Tribune, March 29, 2024)
Rough Design for New Four-Lane Basiliere Bridge Shows Familiar Arches, Vertical Beacons (WHAV, November 17, 2023)
Public attends Basiliere Bridge session (Haverhill Gazette, April 6, 2023)
Basiliere Bridge to Keep Two Lanes Open During Construction; Residents Give Wish List (WHAV, March 13, 2023)
Public meeting on $150 million Basiliere Bridge replacement project (Haverhill Gazette, March 9, 2023)
Replacement of Basiliere Bridge Prominent in State Bridge and Road Spending Plan (WHAV, February 4, 2022)
Repairs to Basiliere Bridge not expected until 2024 (Haverhill Gazette, January 16, 2020)