Commonwealth of Massachusetts
MassDOT is replacing structurally deficient bridges carrying I-495 over the Merrimack River and carrying Industrial Avenue over I-495 in Haverhill and Methuen.

The Haverhill–Methuen Bridge Replacements Project will reconstruct multiple aging bridges along a 1.5-mile section of I-495 in Methuen and Haverhill. The existing bridges were built in the 1960s. They remain safe but are nearing the end of their service life and must be replaced.
This work will improve safety, reduce long-term maintenance needs, and enhance traffic operations along one of the region’s most heavily traveled corridors.
Project Information
Location
I-495 between Methuen and Haverhill
Ward
Ward 7
Project Type
Project Phase
Construction
Anticipated Completion
2030
Project Manager
MassDOT - Highway Division, Christopher P Gagne
The project includes:
I-495 bridges
Industrial Avenue bridges
Route 110/Merrimack Street
Construction updates are provided by MassDOT. Sign up to receive regular updates to your email or visit Traffic and construction updates to view project status and construction and traffic management updates.
MassDOT will maintain traffic throughout construction using staged construction:
Temporary lane shifts, short-term lane drops, rolling roadblocks, and detours may be used during off-peak hours to safely complete work. Advisories and advanced warning signs will be used prior to all traffic impacts.
Construction updates are provided by MassDOT. Sign up to receive regular updates to your email or visit Traffic and construction updates to view project status and construction and traffic management updates.
This project is funded through state and federal programs:
MassDOT welcomes any questions you may have and encourages that you sign up to receive regular updates to your email.
Visit Documents and meeting materials to view all public meetings' flyers, presentations, and minutes.
MassDOT Board Meeting Presentation (February 26, 2025)
401 Water Quality Certification (July 29, 2024)
Amended 401 Water Quality Certification (August 29, 2024)
Army Corps Verification with Plan Set
Ward Hill Ramps to Close Overnights as Needed for New Bridge Foundation (WHAV, July 12, 2026)
I-495 Bridge Work Requires Nightly Lane Closings as Needed (WHAV, June 8, 2026)
Phase 1 of Basiliere Bridge project launches | Haverhill (Eagle Tribune, May 19, 2026)
Interstate 495 Preliminary Bridge Replacement Work Continues with Night Lane Closings (WHAV, February 1, 2026)
Night Lane Closings Coming to Aid I-495 Haverhill-Methuen Bridge Construction (WHAV, January 4, 2026)
I-495 Work Between Methuen and Haverhill Takes Place Overnights This Week (December 14, 2025)
State Adds Another Overnight to Interstate 495 Ramp Closings This Week (November 19, 2025)
Interstate 495 Restrictions Begin as Four Bridges to be Replaced Over Next Few Years (November 16, 2025)
Hearing on I-495 bridge projects Thursday (Eagle Tribune, November 12, 2025)
Hearing on I-495 bridge projects Thursday (CNHI, November 11, 2025)
State Invites Public to Learn of Five-Year Haverhill, Methuen Interstate 495 Bridge Project (November 5, 2025)
Contact Us
Haverhill City Hall
4 Summer Street
Haverhill MA, 01830
Monday - Friday 8:00 - 4:00
Call Center 311 (within city limits)
(978) 358-1311 (outside the city)