Water Supply Emergency

Frequently Asked Questions

What Caused the Water Supply Emergency?

Haverhill is experiencing a water availability emergency due to a prolonged drought.

Prolonged Drought: Approximately two years of insufficient precipitation and declining water levels have substantially reduced available reservoir storage.

Kenoza Lake: Water levels have fallen approximately 11 feet below normal operating elevation for this time of year and 17.5 feet below full.

Millvale Reservoir: Critically low water levels have made supplemental supply very limited.

Crystal Lake: Drought conditions have limited its ability to replenish Kenoza Lake.

Essential Demand: The City must maintain sufficient water supplies for drinking, sanitation, businesses, essential services, and fire protection.

Regional drought classifications do not reflect Haverhill's specific water supply conditions. Rainfall varies geographically, and Haverhill relies primarily on surface-water reservoirs that depend on adequate precipitation to replenish their storage. Unlike neighboring communities that actively withdraw water from the Merrimack River, Haverhill's existing supply is more directly affected by prolonged periods of insufficient rainfall. As a result, improvements in regional drought conditions do not automatically translate into increased water availability for Haverhill.

 

Understanding Haverhill's Water Treatment System

Haverhill's Water Treatment Plant (WTP), located at Kenoza Lake, serves approximately 61,000 residents. The facility utilizes a comprehensive, multistage treatment process designed to protect drinking water quality.

Water Sources: Kenoza Lake serves as the City's primary terminal reservoir, supported by Crystal Lake, Millvale Reservoir, and Round Pond.

Treatment and Filtration: Water undergoes chemical pre-treatment, dissolved air flotation for clarification, sand filtration, and granular activated carbon filtration to remove particles and impurities.

Disinfection and Corrosion Control: Carefully controlled chemical treatment disinfects the water, adjusts water chemistry, and helps protect the distribution system from corrosion.

Professional Oversight: Licensed water treatment operators oversee plant operations, monitor treatment performance, and conduct water quality testing to maintain compliance and provide the highest water quality to the public.

The City's Water Treatment Plant underwent significant upgrades between 2017-2021 to enhance treatment capabilities, improve operational efficiency, and strengthen protections for drinking water quality. The facility is designed to treat water from the City's approved sources using established filtration, disinfection, and corrosion control processes. Introducing new water sources requires careful evaluation of water chemistry, treatment compatibility, and potential impacts on the distribution system to ensure continued compliance with drinking water standards.

 

What Can Haverhill Learn from Flint, Michigan?

Flint, Michigan, serves as a cautionary example of why water quality safeguards, corrosion control, and regulatory oversight are essential when introducing new drinking water sources.

MassDEP's emergency declaration references the drinking water crisis in Flint, Michigan. While we recognize that this comparison may raise understandable concerns, the circumstances facing Haverhill are fundamentally different.

Flint's Crisis: A change in drinking water sources without adequate corrosion control, combined with regulatory and oversight failures, resulted in widespread lead contamination and significant public health consequences.

Haverhill's Emergency: Prolonged drought has depleted the City's available water supplies, requiring the evaluation and development of supplemental sources if drought continues.

Existing Safeguards: Haverhill operates an established water treatment facility with filtration, disinfection, corrosion control, and routine water quality monitoring designed to treat surface water.

Regulatory Oversight: MassDEP is actively overseeing the City's emergency response, requiring engineering evaluations, water quality testing, treatment compatibility assessments, and additional monitoring. While direct withdrawal from the Merrimack River has not yet been authorized, the City continues to work closely with MassDEP to address outstanding requirements and obtain the necessary approvals, ensuring that public health and drinking water quality remain protected.

MassDEP's reference to Flint reinforces an important lesson: introducing a new water source requires careful evaluation of water chemistry, corrosion control, and potential impacts on drinking water quality.

The City is not bypassing these safeguards. Every proposed emergency water source is being evaluated in coordination with MassDEP, with public health and water quality remaining the highest priorities.

 

What Residents Need to Know

Mandatory restrictions on nonessential outdoor water use remain in effect, subject to applicable exceptions.

Residents and businesses are strongly encouraged to:

Comply with all water use restrictions.
Minimize unnecessary indoor water consumption.
Promptly report suspected water leaks.
Follow official City communications for updates.


Every gallon conserved helps preserve Haverhill's remaining water supply while emergency improvements are advanced.

 

What Is the City Doing?

The City is advancing multiple emergency and long-term water supply improvements simultaneously, working closely with MassDEP, engineering professionals, contractors, and neighboring communities.

The City is establishing an emergency interconnection with Methuen to supplement Haverhill's existing supply with treated drinking water.

Routine lead and copper sampling has recently been completed.

Water chemistry compatibility concerns have been resolved with required additional sampling to ensure we meet the highest water quality standards.

MassDEP approval has been received.

The City is under contract with N. Granese & Sons for installation of the interconnection.

Installation of the interconnection piping is scheduled to begin the week of November 23, 2026.

The interconnection is approved to provide up to 1 million gallons to supplement Haverhill’s water supply.

The City is advancing the temporary use of the East Broadway Test Well to supplement existing water supplies while permanent infrastructure improvements are completed.

MassMass DEP Approval: MassDEP has authorized the temporary use of the test well, subject to specific water quality sampling, monitoring, and regulatory conditions.

Pending Authorization: The City is awaiting MassDEP approval for direct withdrawal from the Merrimack River, which would provide an additional emergency water supply beyond the limited quantity currently authorized from the East Broadway Test Well.

Authorized Withdrawal: The approved withdrawal is limited to 600,000 gallons per day (0.6 million gallons per day).

Construction: N. Granese & Sons has been contracted to install the temporary bypass piping.

Installation Schedule: Construction Installation Schedule: is scheduled to begin the week of November 23, 2026

Emergency Supply: The temporary system will provide an additional, limited source of water while the City advances its permanent radial collector well project.

Water Quality Protection: Operation of the test well will remain subject to Mass DEP's established withdrawal limits, water quality requirements, and monitoring conditions.

The City is actively pursuing an emergency temporary water intake from the Merrimack River to supplement its existing water supply during the ongoing drought.

MassDEP Approval: The City is seeking authorization from MassDEP to withdraw water from the proposed emergency intake location. Engineering evaluations, water quality testing, and treatment compatibility assessments are ongoing.

Emergency Construction Authorization: The City has received an emergency procurement waiver from the Massachusetts Division of Capital Asset Management and Maintenance (DCAMM), allowing construction activities to proceed on an expedited basis.

Agency Coordination: The City is working closely with the U.S. Army Corps of Engineers, MassDEP, Massachusetts Department of Conservation and Recreation (DCR), and Massachusetts Division of Fisheries and Wildlife to coordinate environmental requirements, necessary permits, regulatory approvals, and construction activities associated with the emergency water intake.

Construction: Emergency infrastructure improvements are being advanced while the City continues working to satisfy applicable regulatory requirements.

Resident Notification: The City is working to notify residents and property owners who may be directly impacted by construction activities and provide relevant information regarding anticipated work and potential disruptions.

Water Quality Protection: No water will be withdrawn for drinking water supply purposes until the necessary MassDEP authorization has been obtained and applicable water quality requirements have been satisfied.

The City is pursuing construction and regulatory approvals simultaneously to expedite access to an additional emergency water source while maintaining appropriate public health and environmental safeguards.

The City is accelerating engineering and construction of the permanent radial collector well along the Merrimack River to establish a reliable additional drinking water source.

Core & Main is supplying the permanent piping required for the project.

Construction and associated infrastructure improvements are being expedited.

The permanent radial collector well is currently anticipated to be under construction in early April 2027.

This investment will diversify the City's water sources and reduce vulnerability to future drought conditions.

The system is anticipated to be operational by July of 2028, with the potential for earlier completion.

The City is evaluating opportunities to maximize available water supplies from its existing water resources.

How additional water can be accessed and transferred (very limited)

Extremely shallow conditions at Round Pond present challenges for the installation and operation of temporary pumping equipment.

The City is assessing; efforts remain focused on identifying a practical solution to supplement available water supplies.

There is approximately 18 days of water supply in the available volume of Round Pond.

The City is coordinating with MassDEP to implement additional water quality testing and monitoring associated with emergency water supply improvements.

Lead and Copper Sampling: Haverhill completed its routine lead and copper sampling in September 2026.  Additional sampling associated with the Methuen interconnection is being scheduled.

Water Chemistry: Initial compatibility concerns involving the Methuen supply have been resolved.

Pre-Operation Testing: Additional sampling and testing will be conducted as required before introducing new water sources.

Post-Connection Monitoring: Enhanced monitoring will be conducted following activation of emergency sources in accordance with MassDEP requirements.

Routine Compliance: The City will continue its established drinking water testing program alongside any additional monitoring required under the emergency declaration.

Water Quality Standards: All emergency water sources must meet applicable federal and state drinking water quality standards and satisfy MassDEP's testing, treatment, and monitoring requirements before being introduced into the City's drinking water system.

The specific sampling frequencies, testing schedules, and reporting requirements will be established in accordance with MassDEP's directives.

The City continues implementing measures to preserve available supplies and improve system efficiency.

Enforcing mandatory outdoor water restrictions.

Identifying and addressing water leaks.

Advancing water infrastructure and metering improvements.

Evaluating treatment plant efficiency and operational improvements.

Urging the community to continue practicing indoor water conservation - Tips for Indoor Water Conservation

These efforts represent a coordinated response to protect Haverhill's immediate water supply while advancing critical infrastructure investments for the future.

Our Commitment to Haverhill

Haverhill's water supply emergency is the result of extraordinary and prolonged environmental conditions requiring an equally extraordinary response.

The dedicated men and women of the City's Water Department are working alongside engineering professionals, contractors, neighboring communities, and state regulators to address these challenges.

Behind every treatment process, water quality test, emergency installation, and infrastructure improvement are experienced professionals who understand the importance of the services they provide and the trust our community places in them.

These employees are working diligently to maintain safe and reliable drinking water under exceptionally challenging circumstances.

Our immediate responsibility is protecting public health and maintaining essential water service. Our long-term commitment is building a stronger, more resilient water system capable of serving Haverhill for generations to come.

The City will continue providing updates as emergency improvements advance and additional information becomes available.

We sincerely thank Haverhill's residents and businesses for their patience, understanding, and continued conservation efforts during this challenging time.

City of Haverhill
Water Department

Contact Us

Haverhill City Hall
4 Summer Street
Haverhill MA, 01830

Monday - Friday 8:00 - 4:00
Call Center 311 (within city limits)
(978) 358-1311 (outside the city)

Online Service Requests