State Denies River Draw; Haverhill to Take Water from Methuen, City Test Well First (WHAV, November 16, 2026)
Methuen Water Connection
Water Supply Emergency Information
Project Overview
The City is establishing an emergency interconnection with Methuen to supplement Haverhill's existing supply with treated drinking water. The interconnection is approved to provide up to 1 million gallons to supplement Haverhill’s water supply. Water chemistry compatibility concerns have been resolved with required additional sampling to ensure we meet the highest water quality standards.
Project Information
Location
River Street
Ward
Wards 5 & 7
Project Type
Water Supply
Project Phase
Construction
Anticipated Completion
January 2027
Project Manager
Robert E. Ward, DPW Director – Water/Wastewater, rward@haverhillma.gov
John D’Aoust, WTP Facility Manager, jdaoust@haverhillma.gov
Andew Carvalho, Water Maintenance Supervisor, acarvalho@haverhillma.gov
Shaun Burrier, Water/Wastewater Engineer, sburrier@haverhillma.gov
Consultant
Contractor
Construction Updates
Construction is scheduled to begin the week of November 23, 2026.
Anticipated completion in January 2027.
Traffic Changes
Traffic impacts, road closures, and detour information will be provided as construction plans and schedules become available.
Financing
October 2016: City Council authorized $17,168,750 for the planning, design, and construction of the new Radial Collector Well and transmission main.
June 2, 2026: City Council approved a $900,000 loan order for the acquisition of 309 East Broadway.
June 12, 2026: The Water Department conducted a tiered rate study.
State Revolving Fund (SRF): The City has submitted a funding application and is pursuing low-interest financing to help fund the project.
November 18, 2026: The City received an advertisement of procurement waiver from the Department of Capital Asset Municipal Management (DCAMM).
December 2026: The City will request an increase in the original RCW loan order from $17,168,750 to $26,075,850 to advance construction.