Skip to main content Skip to footer

Haverhill Former MGP Site

This page was updated 1.27.2025. See updates from National Grid here: haverhillmgpsite6.wordpress.com

Project Overview

National Grid is in the process of an environmental cleanup at the former Haverhill Manufactured Gas Plant (MGP) Site located at 284 Winter Street in Haverhill, MA (“Site”). The Haverhill Environmental Remediation Project (“Project”) is a result of National Grid’s continued commitment to address environmental issues under the Massachusetts Contingency Plan.

The Project is working closely with local, state, and federal agencies including the Haverhill Conservation Commission, Massachusetts Department of Environmental Protection, and the United States Army Corps of Engineers to ensure that work is properly permitted, safely executed, and complies with environmental and other legal requirements.

Background

From 1853 to 1970, the Haverhill Manufactured Gas Plant, or MGP, used coal and oil to produce manufactured gas. Local consumers used the manufactured gas for the same purposes that we use natural gas today. The gas production process yielded by-products such as tar and oils, some of which are present in the Site subsurface and sediments within the Little River that runs next to the Site.

MGPs were common throughout the Northeast before the construction of the region’s natural gas pipelines, after which MGP operations ended. The former MGP Site operated in Haverhill until 1970.

Since 1977, the downtown Haverhill Project Site has operated as a gasoline service station, fuel oil distribution facility, and car wash.

In 2015, contamination was identified at the Site. Between November of 2019 and now, National Grid has been undertaking a multi-year project to study conditions by collecting soil and groundwater samples from the upland and sediment and surface water samples from the Little River. Because of the location of the contamination (below ground and in the river), there are currently no risks to human receptors, but National Grid has developed a comprehensive action plan to clean up the Site to protect human health and the environment.

Planned Remediation Efforts

The cleanup project will involve a combination of activities in the upland area and work within the Little River. Key activities include:

Upland Remediation: Most activities will occur within the existing parking lot area. These activities include the reduction and removal of benzene from the groundwater through a process of air injection and extraction. A series of wells will be drilled, and a piping network will be installed. The treatment system will inject air into the ground, and will extract and treat the injected air and vapors. In addition, coal tar material will be removed from the soil in certain areas and will be shipped to an approved facility for recycling or disposal. During this time, a temporary cap will be placed in the little river adjacent to the retaining wall. The cap will be made up of geotextile bags filled with gravel with treatment material attached to the bag, and will be placed using a crane.
River Remediation: The temporary cap will be removed and contaminated sediments from the bed of the Little River will be removed by dredging. Because the river is shallow and not very wide, the dredging will be done using small, specialized equipment. Some of the vegetation along the banks may be removed or pruned, and debris from the river will be removed before the dredging. After dredging, a long-term cap will be placed in the river.

Next Steps

The Project will occur in stages starting in late 2024 and continuing into 2026.   It will be conducted in accordance with the Massachusetts Contingency Plan or MCP, which regulates how contaminated sites must be assessed and cleaned up.   In June 2024, a Phase IV Remedy Implementation Plan with drawings and specifications for the Project was submitted to the Massachusetts Department of Environmental Protection or MassDEP, a State agency whose primary responsibility is to safeguard the state’s environment.  A link to the Remedy Implementation Plan, as well as previous MCP filings for this Project, is provided below.. In addition, a Notice of Intent for the upland remediation and temporary cap has been filed with the Haverhill Conservation Commission and with MassDEP. Additional reporting and permits will be required at the local, state, and federal levels; copies of the reports and permits will be provided on this website. You can also go to the MassDEP files directly at: Energy & Environmental Affairs Data Portal

The remediation construction activities are anticipated to occur in phases spanning from late-2024 until mid-2027.

National Grid will coordinate with property owners in this area as well as begin the necessary permitting efforts associated with the Project.

Additional Resources / Public Notices

National Grid anticipates that the Project will be reviewed under the Massachusetts Environmental Policy Act (MEPA) as well as local, state and federal permitting agencies. As public hearing and participation sessions are scheduled, information will be posted below.

Massachusetts Department of Environmental Protection Submitted Files Below:

Community Outreach

National Grid is committed to keeping you informed of construction activities associated with the Project. For more information, please contact Jesse Edmands at 781-906-3987 or email Jesse.Edmands@nationalgrid.com

Local Permitting:

#33-1577 Boston Gas Company for 284 Winter St (Parcel ID: 307-2-1) Proposed site remediation associated with past manufactured gas facility
    Uploaded 09.23.24:     Notice of Intent Application
    Uploaded 10.07.24:     Con Com Presentation
    Uploaded 12.05.24:     Peer Review
    Uploaded 01.16.25:     Peer Review #2     Order of Conditions

See updates from National Grid here: haverhillmgpsite6.wordpress.com

Contact Us

Haverhill City Hall
4 Summer Street
Haverhill MA, 01830

Monday - Friday 8:00 - 4:00
Call Center 311 (within city limits)
(978) 358-1311 (outside the city)

This website uses cookies to enhance usability and provide you with a more personal experience. By using this website, you agree to our use of cookies as explained in our Privacy Policy.